A) The NPV profile graph for a normal project will generally have a positive (upward) slope as the life of the project increases.
B) An NPV profile graph is designed to give decision makers an idea about how a project's risk varies with its life.
C) An NPV profile graph is designed to give decision makers an idea about how a project's contribution to the firm's value varies with the cost of capital.
D) We cannot draw a project's NPV profile unless we know the appropriate cost of capital for use in evaluating the project's NPV.
E) An NPV profile graph shows how a project's payback varies as the cost of capital changes.
Correct Answer
verified
Multiple Choice
A) If Project S has a positive NPV, Project L must also have a positive NPV.
B) If the cost of capital falls, each project's IRR will increase.
C) If the cost of capital increases, each project's IRR will decrease.
D) If Projects S and L have the same NPV at the current cost of capital, 10%, then Project L, the one with the lower IRR, would have a higher NPV if the cost of capital used to evaluate the projects declined.
E) Project S must have a higher NPV than Project L.
Correct Answer
verified
Multiple Choice
A) You should delay a decision until you have more information on the projects, even if this means that a competitor might come in and capture this market.
B) You should recommend Project R, because at the new cost of capital it will have the higher NPV.
C) You should recommend Project K, because at the new cost of capital it will have the higher NPV.
D) You should recommend Project R because it will have both a higher IRR and a higher NPV under the new conditions.
E) You should reject both projects because they will both have negative NPVs under the new conditions.
Correct Answer
verified
True/False
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) $54.62
B) $57.49
C) $60.52
D) $63.54
E) $66.72
Correct Answer
verified
True/False
Correct Answer
verified
True/False
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) The crossover rate must be greater than 10%.
B) If the cost of capital is 8%, Project X will have the higher NPV.
C) If the cost of capital is 18%, Project Y will have the higher NPV.
D) Project X is larger in the sense that it has the higher initial cost.
E) The crossover rate must be less than 10%.
Correct Answer
verified
Multiple Choice
A) One defect of the IRR method is that it does not take account of the time value of money.
B) One defect of the IRR method is that it does not take account of the cost of capital.
C) One defect of the IRR method is that it values a dollar received today the same as a dollar that will not be received until sometime in the future.
D) One defect of the IRR method is that it assumes that the cash flows to be received from a project can be reinvested at the IRR itself, and that assumption is often not valid.
E) One defect of the IRR method is that it does not take account of cash flows over a project's full life.
Correct Answer
verified
Multiple Choice
A) If the cost of capital is greater than the crossover rate, then the IRR and the NPV criteria will not result in a conflict between the projects.The same project will rank higher by both criteria.
B) If the cost of capital is less than the crossover rate, then the IRR and the NPV criteria will not result in a conflict between the projects.The same project will rank higher by both criteria.
C) For a conflict to exist between NPV and IRR, the initial investment cost of one project must exceed the cost of the other.
D) For a conflict to exist between NPV and IRR, one project must have an increasing stream of cash flows over time while the other has a decreasing stream.If both sets of cash flows are increasing or decreasing, then it would be impossible for a conflict to exist, even if one project is larger than the other.
E) If the two projects' NPV profiles do not cross, then there will be a sharp conflict as to which one should be selected.
Correct Answer
verified
Multiple Choice
A) To find the MIRR, we first compound cash flows at the regular IRR to find the TV, and then we discount the TV at the cost of capital to find the PV.
B) The NPV and IRR methods both assume that cash flows can be reinvested at the cost of capital.However, the MIRR method assumes reinvestment at the MIRR itself.
C) If two projects have the same cost, and if their NPV profiles cross in the upper right quadrant, then the project with the higher IRR probably has more of its cash flows coming in the later years.
D) If two projects have the same cost, and if their NPV profiles cross in the upper right quadrant, then the project with the lower IRR probably has more of its cash flows coming in the later years.
E) For a project with normal cash flows, any change in the cost of capital will change both the NPV and the IRR.
Correct Answer
verified
Multiple Choice
A) The lower the cost of capital used to calculate a project's NPV, the lower the calculated NPV will be.
B) If a project's NPV is less than zero, then its IRR must be less than the cost of capital.
C) If a project's NPV is greater than zero, then its IRR must be less than zero.
D) The NPV of a relatively low-risk project should be found using a relatively high cost of capital.
E) A project's NPV is found by compounding the cash inflows at the IRR to find the terminal value (TV) , then discounting the TV at the cost of capital.
Correct Answer
verified
Multiple Choice
A) The higher the cost of capital used to calculate the NPV, the lower the calculated NPV will be.
B) If a project's NPV is greater than zero, then its IRR must be less than the cost of capital.
C) If a project's NPV is greater than zero, then its IRR must be less than zero.
D) The NPVs of relatively risky projects should be found using relatively low costs of capital.
E) A project's NPV is generally found by compounding the cash inflows at the cost of capital to find the terminal value (TV) , then discounting the TV at the IRR to find its PV.
Correct Answer
verified
Multiple Choice
A) One defect of the IRR method versus the NPV is that the IRR does not take account of the time value of money.
B) One defect of the IRR method versus the NPV is that the IRR does not take account of the cost of capital.
C) One defect of the IRR method versus the NPV is that the IRR values a dollar received today the same as a dollar that will not be received until sometime in the future.
D) One defect of the IRR method versus the NPV is that the IRR does not take proper account of differences in the sizes of projects.
E) One defect of the IRR method versus the NPV is that the IRR does not take account of cash flows over a project's full life.
Correct Answer
verified
True/False
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) You should delay a decision until you have more information on the projects, even if this means that a competitor might come in and capture this market.
B) You should recommend Project R, because at the new cost of capital it will have the higher NPV.
C) You should recommend Project K, because at the new cost of capital it will have the higher NPV.
D) You should recommend Project K because it has the higher IRR and will continue to have the higher IRR even at the new cost of capital.
E) You should reject both projects because they will both have negative NPVs under the new conditions.
Correct Answer
verified
Multiple Choice
A) If Project A has a higher IRR than Project B, then Project A must also have a higher NPV.
B) The IRR calculation implicitly assumes that all cash flows are reinvested at the cost of capital.
C) The IRR calculation implicitly assumes that cash flows are withdrawn from the business rather than being reinvested in the business.
D) If a project has normal cash flows and its IRR exceeds its cost of capital, then the project's NPV must be positive.
E) If Project A has a higher IRR than Project B, then Project A must have the lower NPV.
Correct Answer
verified
Showing 21 - 40 of 52
Related Exams