Correct Answer
verified
Multiple Choice
A) 1.61 years
B) 1.79 years
C) 1.99 years
D) 2.22 years
E) 2.44 years
Correct Answer
verified
Multiple Choice
A) The crossover rate must be less than 10%.
B) The crossover rate must be greater than 10%.
C) If the WACC is 8%, Project X will have the higher NPV.
D) If the WACC is 18%, Project Y will have the higher NPV.
E) Project X is larger in the sense that it has the higher initial cost.
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) You should reject both projects because they will both have negative NPVs under the new conditions.
B) You should delay a decision until you have more information on the projects, even if this means that a competitor might come in and capture this market.
C) You should recommend Project L, because at the new WACC it will have the higher NPV.
D) You should recommend Project S, because at the new WACC it will have the higher NPV.
E) You should recommend Project L because it will have the higher IRR at the new WACC.
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) $265.65
B) $278.93
C) $292.88
D) $307.52
E) $322.90
Correct Answer
verified