A) One drawback of the regular payback is that this method does not take account of cash flows beyond the payback period.
B) If a project's payback is positive, then the project should be accepted because it must have a positive NPV.
C) The regular payback ignores cash flows beyond the payback period, but the discounted payback method overcomes this problem.
D) One drawback of the discounted payback is that this method does not consider the time value of money, while the regular payback overcomes this drawback.
E) The shorter a project's payback period, the less desirable the project is normally considered to be by this criterion.
Correct Answer
verified
Multiple Choice
A) If a project's IRR is equal to its cost of capital, then under all reasonable conditions, the project's IRR must be negative.
B) If a project's IRR is equal to its cost of capital, then under all reasonable conditions the project's NPV must be zero.
C) There is no necessary relationship between a project's IRR, its cost of capital, and its NPV.
D) When evaluating mutually exclusive projects, those projects with relatively long lives will tend to have relatively high NPVs when the cost of capital is relatively high.
E) If a project's IRR is equal to its cost of capital, then, under all reasonable conditions, the project's NPV must be negative.
Correct Answer
verified
Multiple Choice
A) 1.91 years
B) 2.12 years
C) 2.36 years
D) 2.59 years
E) 2.85 years
Correct Answer
verified
Multiple Choice
A) If Project A has a higher IRR than Project B, then Project A must also have a higher NPV.
B) The IRR calculation implicitly assumes that all cash flows are reinvested at the cost of capital.
C) The IRR calculation implicitly assumes that cash flows are withdrawn from the business rather than being reinvested in the business.
D) If a project has normal cash flows and its IRR exceeds its cost of capital, then the project's NPV must be positive.
E) If Project A has a higher IRR than Project B, then Project A must have the lower NPV.
Correct Answer
verified
Multiple Choice
A) $188.68
B) $198.61
C) $209.07
D) $219.52
E) $230.49
Correct Answer
verified
Multiple Choice
A) The lower the cost of capital used to calculate a project's NPV, the lower the calculated NPV will be.
B) If a project's NPV is less than zero, then its IRR must be less than the cost of capital.
C) If a project's NPV is greater than zero, then its IRR must be less than zero.
D) The NPV of a relatively low-risk project should be found using a relatively high cost of capital.
E) A project's NPV is found by compounding the cash inflows at the IRR to find the terminal value (TV) , then discounting the TV at the cost of capital.
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) $134.79
B) $141.89
C) $149.36
D) $164.29
E) $205.36
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) 1.42 years
B) 1.58 years
C) 1.75 years
D) 1.93 years
E) 2.12 years
Correct Answer
verified
Multiple Choice
A) $265.65
B) $278.93
C) $292.88
D) $307.52
E) $322.90
Correct Answer
verified
Multiple Choice
A) The IRR method can never be subject to the multiple IRR problem, while the MIRR method can be.
B) One reason some people prefer the MIRR to the regular IRR is that the MIRR is based on a generally more reasonable reinvestment rate assumption.
C) The higher the cost of capital, the shorter the discounted payback period.
D) The MIRR method assumes that cash flows are reinvested at the crossover rate.
E) The MIRR and NPV decision criteria can never conflict.
Correct Answer
verified
Multiple Choice
A) A project's MIRR is always less than its regular IRR.
B) If a project's IRR is greater than its cost of capital, then the MIRR will be less than the IRR.
C) If a project's IRR is greater than its cost of capital, then the MIRR will be greater than the IRR.
D) To find a project's MIRR, we compound cash inflows at the IRR and then discount the terminal value back to t = 0 at the cost of capital.
E) A project's MIRR is always greater than its regular IRR.
Correct Answer
verified
True/False
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) Since the smaller project has the higher IRR, the two projects' NPV profiles will cross, and the larger project will look better based on the NPV at all positive values of the cost of capital.
B) If the company uses the NPV method, it will tend to favor smaller, shorter-term projects over larger, longer-term projects, regardless of how high or low the cost of capital is.
C) Since the smaller project has the higher IRR but the larger project has the higher NPV at a zero discount rate, the two projects' NPV profiles will cross, and the larger project will have the higher NPV if the cost of capital is less than the crossover rate.
D) Since the smaller project has the higher IRR and the larger NPV at a zero discount rate, the two projects' NPV profiles will cross, and the smaller project will look better if the cost of capital is less than the crossover rate.
E) Since the smaller project has the higher IRR, the two projects' NPV profiles cannot cross, and the smaller project's NPV will be higher at all positive values of the cost of capital.
Correct Answer
verified
Multiple Choice
A) If two projects are mutually exclusive, then they are likely to have multiple IRRs.
B) If a project is independent, then it cannot have multiple IRRs.
C) Multiple IRRs can occur only if the signs of the cash flows change more than once.
D) If a project has two IRRs, then the smaller one is the one that is most relevant, and it should be accepted and relied upon.
E) For a project to have more than one IRR, then both IRRs must be greater than the cost of capital.
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) The payback method is generally regarded by academics as being the best single method for evaluating capital budgeting projects.
B) The discounted payback method is generally regarded by academics as being the best single method for evaluating capital budgeting projects.
C) The net present value method (NPV) is generally regarded by academics as being the best single method for evaluating capital budgeting projects.
D) The modified internal rate of return method (MIRR) is generally regarded by academics as being the best single method for evaluating capital budgeting projects.
E) The internal rate of return method (IRR) is generally regarded by academics as being the best single method for evaluating capital budgeting projects.
Correct Answer
verified
Multiple Choice
A) 14.05%
B) 15.61%
C) 17.34%
D) 19.27%
E) 21.20%
Correct Answer
verified
Showing 81 - 100 of 107
Related Exams