Filters
Question type

Study Flashcards

  -The direct labor time variance is A)  $6,000 favorable B)  $6,000 unfavorable C)  $33,000 unfavorable D)  $33,000 favorable -The direct labor time variance is


A) $6,000 favorable
B) $6,000 unfavorable
C) $33,000 unfavorable
D) $33,000 favorable

E) All of the above
F) B) and D)

Correct Answer

verifed

verified

Which of the following would not lend itself to applying direct labor variances?


A) help desk assistant
B) research and development scientist
C) customer service personnel
D) telemarketer

E) All of the above
F) B) and C)

Correct Answer

verifed

verified

Changes in technology, machinery, or production methods may make past cost data irrelevant when setting standards.

A) True
B) False

Correct Answer

verifed

verified

Favorable volume variances may be harmful when


A) machine repairs cause work stoppages
B) supervisors fail to maintain an even flow of work
C) production in excess of normal capacity cannot be sold
D) All of these choices

E) A) and C)
F) B) and C)

Correct Answer

verifed

verified

If the standard to produce a given amount of product is 500 direct labor hours at $15 and the actual is 600 hours at $17, the rate variance is $1,200 favorable.

A) True
B) False

Correct Answer

verifed

verified

If the actual quantity of direct materials used in producing a commodity differs from the standard quantity, the variance is a


A) controllable variance
B) price variance
C) quantity variance
D) rate variance

E) B) and D)
F) B) and C)

Correct Answer

verifed

verified

The principle of exceptions allows managers to focus on correcting variances between standard costs and actual costs.

A) True
B) False

Correct Answer

verifed

verified

While setting standards, managers should never allow for spoilage or machine breakdowns in their calculations.

A) True
B) False

Correct Answer

verifed

verified

Standards are more widely used for nonmanufacturing activities than for manufacturing activities.

A) True
B) False

Correct Answer

verifed

verified

Which of the following is not a reason for a direct materials quantity variance?


A) malfunctioning equipment
B) purchasing of inferior raw materials
C) increased material cost per unit
D) spoilage of materials

E) A) and C)
F) A) and B)

Correct Answer

verifed

verified

Match each of the following descriptions with the term (a-e) it describes. -An example is the number of customer complaints


A) Ideal standard
B) Nonfinancial performance measure
C) Currently attainable standard
D) Unfavorable cost variance
E) Favorable cost variance

F) B) and E)
G) A) and B)

Correct Answer

verifed

verified

Jaxson Corporation has the following data related to direct labor costs for September: actual costs are 10,200 hours at $15.75 per hour and standard costs are 10,800 hours at $15.50 per hour.​What is the direct labor time variance?


A) $9,300 favorable
B) $9,300 unfavorable
C) $9,450 favorable
D) $9,450 unfavorable

E) A) and C)
F) A) and D)

Correct Answer

verifed

verified

Use this information to answer the questions that follow. ​ The standard factory overhead rate is $10 per direct labor hour ($8 for variable factory overhead and $2 for fixed factory overhead) based on 100% of normal capacity of 30,000 direct labor hours. The standard cost and the actual cost of factory overhead for the production of 5,000 units during May were as follows: ​​ Use this information to answer the questions that follow. ​ The standard factory overhead rate is $10 per direct labor hour ($8 for variable factory overhead and $2 for fixed factory overhead)  based on 100% of normal capacity of 30,000 direct labor hours. The standard cost and the actual cost of factory overhead for the production of 5,000 units during May were as follows: ​​    -What is the fixed factory overhead volume variance? A)  $12,500 favorable B)  $10,000 unfavorable C)  $12,500 unfavorable D)  $10,000 favorable -What is the fixed factory overhead volume variance?


A) $12,500 favorable
B) $10,000 unfavorable
C) $12,500 unfavorable
D) $10,000 favorable

E) A) and C)
F) A) and B)

Correct Answer

verifed

verified

The fact that workers are unable to meet a properly determined direct labor standard is sufficient cause to change the standard.

A) True
B) False

Correct Answer

verifed

verified

The unfavorable volume variance may be due to all of the following factors except


A) failure to maintain an even flow of work
B) machine breakdowns
C) unexpected increases in the cost of utilities
D) failure to obtain enough sales orders

E) All of the above
F) A) and B)

Correct Answer

verifed

verified

Use this information for Stringer Company to answer the questions that follow. ​The following data are given for Stringer Company: ​ Use this information for Stringer Company to answer the questions that follow. ​The following data are given for Stringer Company: ​    Overhead is applied on standard labor hours. -The direct materials quantity variance is A)  $22,800 favorable B)  $22,800 unfavorable C)  $52,000 favorable D)  $52,000 unfavorable Overhead is applied on standard labor hours. -The direct materials quantity variance is


A) $22,800 favorable
B) $22,800 unfavorable
C) $52,000 favorable
D) $52,000 unfavorable

E) B) and D)
F) C) and D)

Correct Answer

verifed

verified

Normal standards allow for normal production difficulties and mistakes.

A) True
B) False

Correct Answer

verifed

verified

Match each of the following descriptions with the term (a-e) it describes. -Actual cost < standard cost at actual volumes


A) Ideal standard
B) Nonfinancial performance measure
C) Currently attainable standard
D) Unfavorable cost variance
E) Favorable cost variance

F) A) and B)
G) A) and C)

Correct Answer

verifed

verified

Compute the standard cost for one hat, based on the following standards for each hat: Compute the standard cost for one hat, based on the following standards for each hat:

Correct Answer

verifed

verified

Match each of the following descriptions with the term (a-e) it describes. -Actual cost > standard cost at actual volumes


A) Ideal standard
B) Nonfinancial performance measure
C) Currently attainable standard
D) Unfavorable cost variance
E) Favorable cost variance

F) A) and B)
G) A) and C)

Correct Answer

verifed

verified

Showing 101 - 120 of 174

Related Exams

Show Answer