Filters
Question type

Study Flashcards

The option to abandon a project is a real option,but a call option on a stock is not a real option.

A) True
B) False

Correct Answer

verifed

verified

Real options are options to buy real assets,especially stocks,rather than interest-bearing assets,like bonds.

A) True
B) False

Correct Answer

verifed

verified

Which one of the following is an example of a "flexibility" option?


A) A company has an option to invest in a project today or to wait for a year before making the commitment.
B) A company has an option to close down an operation if it turns out to be unprofitable.
C) A company agrees to pay more to build a plant in order to be able to change the plant's inputs and/or outputs at a later date if conditions change.
D) A company invests in a project today to gain knowledge that may enable it to expand into different markets at a later date.
E) A company invests in a jet aircraft so that its CEO,who must travel frequently,can arrive for distant meetings feeling less tired than if he had to fly a commercial airline.

F) None of the above
G) A) and D)

Correct Answer

verifed

verified

Tutor.com is considering a plan to develop an online finance tutoring package that has the cost and revenue projections shown below.One of Tutor's larger competitors,Online Professor (OP) ,is expected to do one of two things in Year 5: (1) develop its own competing program,which will put Tutor's program out of business,or (2) offer to buy Tutor's program if it decides that this would be less expensive than developing its own program.Tutor thinks there is a 35% probability that its program will be purchased for $7.0 million and a 65% probability that it won't be bought,and thus the program will simply be closed down with no salvage value.What is the estimated net present value of the project (in thousands) at a WACC = 9.0%,giving consideration to the potential future purchase? Do not round intermediate calculations. WACC=9.0%\mathrm{WACC}=\quad 9.0 \% 012345 Original project: $3,500$600$600$600$600$600\begin{array}{ll}&0&1&2&3&4&5\\\hline\text { Original project: }&-\$3,500&\$600&\$600&\$600&\$600&\$600\end{array}  Future Prob.  Buys 35%$7,000 Doesn’t buy 65%$0\begin{array}{ll}\text { Future} &\text { Prob. }\\\text { Buys } & 35 \% &&\$7,000\\\text { Doesn't buy } & 65 \%&&\$0\end{array}


A) 0$532.65
B) 0$468.73
C) 0$426.12
D) 0$511.35
E) 0$383.51

F) C) and D)
G) A) and E)

Correct Answer

verifed

verified

The following are all examples of real options that are discussed in the text: (1)protection options, (2)flexibility options, (3)timing options,and (4)abandonment options.

A) True
B) False

Correct Answer

verifed

verified

The following 2 problems must be kept together. The first problem can be used alone, but use the second problem ONLY if the first problem is also used. Exhibit 13.1 Texas Wildcatters Inc. (TWI) is in the business of finding and developing oil properties, then selling the successful ones to major oil companies. It is now considering a new potential field, and its geologists have developed the following data, shown in thousands of dollars. * t = 0 A $350 feasibility study would be conducted at t = 0. The results of this study would determine if the company should commence drilling operations or make no further investment and abandon the project. There is an 80% probability that the feasibility study would indicate that an exploratory well should be drilled. There is a 20% probability that no further work would be done. * t = 1 If the feasibility study indicates good potential, the firm would spend $1,200 at t = 1 to drill an exploratory well. The best estimate is that there is a 60% probability that the exploratory well would indicate good potential and thus that further work would be done, and a 40% probability that the outlook would be poor and the project would be abandoned. * t = 2 If the exploratory well tests positive, the firm would go ahead and spend $8,000 to obtain an accurate estimate of the amount of oil in the field at t = 2. * t = 3 If the full drilling program is carried out, there is a 50% probability of finding a lot of oil and receiving $25,000 cash inflow at t = 3, and a 50% probability of finding less oil and then receiving only a $8,000 inflow. * Since the project is considered to be quite risky, a 18.00% cost of capital is used. -Refer to Exhibit 13.1.What is the project's expected NPV,in thousands of dollars? ?


A) 0$1,033.81
B) 0$719.18
C) 0$854.02
D) 0$898.97
E) 0$943.92

F) B) and D)
G) C) and D)

Correct Answer

verifed

verified

For planning purposes,managers must forecast the total capital budget because the amount of capital raised affects the WACC.

A) True
B) False

Correct Answer

verifed

verified

The true expected value of a project with a growth option is the expected NPV of the project (including the value of the option)less the cost of obtaining that option.

A) True
B) False

Correct Answer

verifed

verified

Carlson Inc.is evaluating a project in India that would require a $5.8 million investment today (t = 0) .The after-tax cash flows would depend on whether India imposes a new property tax.There is a 50-50 chance that the tax will pass,in which case the project will produce after-tax cash flows of $1,350,000 at the end of each of the next 5 years.If the tax doesn't pass,the after-tax cash flows will be $1,800,000 for 5 years.The project has a WACC of 10.4%.The firm would have the option to abandon the project 1 year from now,and if it is abandoned,the firm would receive the expected $1.35 million cash flow at t = 1 and would also sell the property for $4.45 million at t = 1.If the project is abandoned,the company would receive no further cash inflows from it.What is the value (in thousands) of this abandonment option? Do not round intermediate calculations.


A) $99
B) $70
C) $94
D) $108
E) $89

F) A) and C)
G) B) and C)

Correct Answer

verifed

verified

It is not possible for abandonment options to decrease a project's risk as measured by the project's coefficient of variation.

A) True
B) False

Correct Answer

verifed

verified

Real options are most valuable when the underlying source of risk--such as uncertainty about unit sales,or the sales price,or input costs--is very low.

A) True
B) False

Correct Answer

verifed

verified

Sheehan Inc.is deciding whether to invest in a project today or to postpone the decision until next year.The project has a positive expected NPV,but its cash flows might turn out to be lower than expected,in which case the NPV could be negative.No competitors are likely to invest in a similar project if the firm decides to wait.Which of the following statements best describes the issues that the firm faces when considering this investment timing option?


A) The investment timing option would not affect the cash flows and therefore would have no impact on the project's risk.
B) The more uncertainty about the future cash flows,the more logical it is to go ahead with this project today.
C) Since the project has a positive expected NPV today,this means that its expected NPV will be even higher if the firm chooses to wait a year.
D) Since the project has a positive expected NPV today,this means that it should be accepted in order to lock in that NPV.
E) Waiting would probably reduce the project's risk.

F) All of the above
G) B) and E)

Correct Answer

verifed

verified

Real options are valuable,and that value is correctly captured by a traditional NPV analysis.Therefore,there is no reason to consider real options separately from the NPV analysis.

A) True
B) False

Correct Answer

verifed

verified

The following are all examples of real options that are discussed in the text: (1)growth options, (2)flexibility options, (3)timing options,and (4)abandonment options.

A) True
B) False

Correct Answer

verifed

verified

Lindley Corp.is considering a new product that would require an investment of $10.5 million now,at t = 0.If the new product is well received,then the project would produce after-tax cash flows of $5.3 million at the end of each of the next 3 years (t = 1,2,3) ,but if the market did not like the product,then the cash flows would be only $2.6 million per year.There is a 50% probability that the market will be good.The firm could delay the project for a year while it conducts a test to determine if demand is likely to be strong or weak.The project's cost and expected annual cash flows would be the same whether the project is delayed or not.The project's WACC is 9.2%.What is the value (in thousands) of the project after considering the investment timing option? Do not round intermediate calculations. ?


A) $1,248
B) $985
C) $1576
D) $1,445
E) $1,313

F) None of the above
G) B) and C)

Correct Answer

verifed

verified

An important part of the capital budgeting process is the post-audit,which involves comparing the actual results with those predicted by the project's sponsors and explaining why any differences occurred.

A) True
B) False

Correct Answer

verifed

verified

The following are all examples of real options that are discussed in the text: (1)natural resource options, (2)flexibility options, (3)timing options,and (4)abandonment options.

A) True
B) False

Correct Answer

verifed

verified

Which one of the following will NOT increase the value of a real option?


A) Lengthening the time during which a real option must be exercised.
B) An increase in the volatility of the underlying source of risk.
C) An increase in the risk-free rate.
D) An increase in the cost of obtaining the real option.
E) A decrease in the probability that a competitor will enter the market of the project in question.

F) B) and C)
G) A) and E)

Correct Answer

verifed

verified

Traditionally,an NPV analysis assumes that projects will be accepted or rejected,which implies that they will be undertaken now or never.However,in practice,companies sometimes have a third choice--delay the decision until later,when more information will be available.Because the analysis extends out at least one additional year from the original analysis,it is unlikely that the firm would ever delay a project--particularly given the loss of the "first mover advantage."

A) True
B) False

Correct Answer

verifed

verified

The optimal capital budget is the size of the capital budget where the rate of return on the marginal project is equal to the marginal cost of capital.

A) True
B) False

Correct Answer

verifed

verified

Showing 21 - 40 of 41

Related Exams

Show Answer