Filters
Question type

Study Flashcards

Assuming that the standard fixed overhead rate is based on full capacity, the cost of available but unused productive capacity is indicated by the


A) fixed factory overhead volume variance
B) direct labor time variance
C) direct labor rate variance
D) variable factory overhead controllable variance

E) A) and D)
F) B) and C)

Correct Answer

verifed

verified

The standard factory overhead rate is $10 per direct labor hour ($8 for variable factory overhead and $2 for fixed factory overhead) based on 100% of normal capacity of 30,000 direct labor hours. The standard cost and the actual cost of factory overhead for the production of 5,000 units during May were as follows: The standard factory overhead rate is $10 per direct labor hour ($8 for variable factory overhead and $2 for fixed factory overhead)  based on 100% of normal capacity of 30,000 direct labor hours. The standard cost and the actual cost of factory overhead for the production of 5,000 units during May were as follows:   What is the amount of the variable factory overhead controllable variance? A)  $10,000 favorable B)  $2,500 unfavorable C)  $10,000 unfavorable D)  $2,500 favorable What is the amount of the variable factory overhead controllable variance?


A) $10,000 favorable
B) $2,500 unfavorable
C) $10,000 unfavorable
D) $2,500 favorable

E) A) and C)
F) B) and C)

Correct Answer

verifed

verified

Robin Company purchased and used 520 pounds of direct materials to produce a product with a 510 pound standard direct materials requirement. The standard materials price is $2.10 per pound. The actual materials price was $2.00 per pound. Prepare the journal entries to record: (1) the purchase of the materials (2) the material entering production.

Correct Answer

verifed

verified

The most effective means of presenting standard factory overhead cost variance data is through a factory overhead cost variance report.

A) True
B) False

Correct Answer

verifed

verified

Japan Company produces lamps that require 2.25 standard hours per unit at an hourly rate of $15.00 per hour. Production of 7,700 units required 19,250 hours at an hourly rate of $14.90 per hour.  What is the direct labor? (a) rate variance (b) time variance (c) total cost variance?

Correct Answer

verifed

verified

(a) Rate variance = ($14.90 - ...

View Answer

Aquatic Corp.'s standard material requirement to produce one Model 2000 is 15 pounds of material @ $110.00 per pound. Last month, Aquatic purchased 170,000 pounds of material at a total cost of $17,850,000.  It used 162,000 pounds to produce 10,000 units of Model 2000.   Calculate the materials price variance and materials quantity variance, and indicate whether each variance is favorable or unfavorable.

Correct Answer

verifed

verified

Actual cost = $17,850,000/170,000 pounds...

View Answer

If a company records inventory purchases at standard cost and also records purchase price variances, prepare the  journal entry for a purchase of widgets that were bought at $7.45 per unit and have a standard cost of $7.15.  The total amount owed to the vendor for this purchase is $33,525.

Correct Answer

verifed

verified

Changes in technology, machinery, or production methods may make past cost data irrelevant when setting standards.

A) True
B) False

Correct Answer

verifed

verified

Which of the following is not a reason for a direct materials quantity variance?


A) malfunctioning equipment
B) purchasing of inferior raw materials
C) increased material cost per unit
D) spoilage of materials

E) All of the above
F) B) and C)

Correct Answer

verifed

verified

The following information is for the standard and actual costs for the Happy Corporation: Standard Costs: Budgeted units of production - 16,000 [80% (or normal) capacity] Standard labor hours per unit - 4 Standard labor rate - $26 per hour Standard material per unit - 8 lbs. Standard material cost - $12 per pound Standard variable overhead rate - $15 per labor hour Budgeted fixed overhead - $640,000 Fixed overhead rate is based on budgeted labor hours at 80% (or normal) capacity. Actual Cost: Actual production - 16,500 units Actual material purchased and used - 130,000 pounds Actual total material cost - $1,600,000 Actual labor - 65,000 hours Actual total labor costs - $1,700,000 Actual variable overhead - $1,000,000 Actual fixed overhead - $640,000 Determine: (a) the direct materials quantity variance, price variance, and total cost variance (b) the direct labor time variance, rate variance, and total cost variance (c) the factory overhead volume variance, controllable variance, and total factory overhead cost variance. (Note: If following text formulas, do not round interim calculations.)

Correct Answer

verifed

verified

(a) Direct materials...

View Answer

  *Actual hours are equal to standard hours for units produced. The total factory overhead cost variance is: A)  $4,866.75 unfavorable B)  $4,866.75 favorable C)  $8,981.75 favorable D)  $8,981.75 unfavorable *Actual hours are equal to standard hours for units produced. The total factory overhead cost variance is:


A) $4,866.75 unfavorable
B) $4,866.75 favorable
C) $8,981.75 favorable
D) $8,981.75 unfavorable

E) All of the above
F) C) and D)

Correct Answer

verifed

verified

Normally, standard costs should be revised when labor rates change to incorporate new union contracts.

A) True
B) False

Correct Answer

verifed

verified

The following data relate to direct labor costs for March: Rate: standard, $12.00; actual, $12.25 Hours: standard, 18,500; actual, 17,955 Units of production: 9,450 Calculate the direct labor rate variance.


A) $4,488.75 unfavorable
B) $6,851.25 favorable
C) $4,488.75 favorable
D) $6,851.25 unfavorable

E) A) and B)
F) A) and C)

Correct Answer

verifed

verified

The following data relate to direct labor costs for the current period: The following data relate to direct labor costs for the current period:   What is the direct labor time variance? A)  $18,000 favorable B)  $18,000 unfavorable C)  $17,550 unfavorable D)  $17,550 favorable What is the direct labor time variance?


A) $18,000 favorable
B) $18,000 unfavorable
C) $17,550 unfavorable
D) $17,550 favorable

E) None of the above
F) A) and B)

Correct Answer

verifed

verified

Which of the following is not a reason standard costs are separated into two components?


A) The price and quantity variances need to be identified separately to correct the actual major differences
B) Identifying variances determines which manager must find a solution to major discrepancies
C) If a negative variance is overshadowed by a favorable variance, managers may overlook potential corrections
D) Variances bring attention to discrepancies in the budget and require managers to revise budgets closer to actual results

E) B) and C)
F) A) and D)

Correct Answer

verifed

verified

Standards are designed to evaluate price and quantity variances separately.

A) True
B) False

Correct Answer

verifed

verified

The following data is given for the Taylor Company: The following data is given for the Taylor Company:    Overhead is applied based on standard labor hours.  Compute the direct labor rate and time variances for Taylor Company. Overhead is applied based on standard labor hours. Compute the direct labor rate and time variances for Taylor Company.

Correct Answer

verifed

verified

Direct labor rate variance:  $...

View Answer

Compute the standard cost for one hat, based on the following standards for each hat: Compute the standard cost for one hat, based on the following standards for each hat:

Correct Answer

verifed

verified

Because accountants have financial expertise, they are the only ones that are able to set standard costs for the production area.

A) True
B) False

Correct Answer

verifed

verified

The standard factory overhead rate is $7.50 per machine hour ($6.20 for variable factory overhead and $1.30 for fixed factory overhead) based on 100% of normal capacity of 80,000 machine hours. The standard cost and the actual cost of factory overhead for the production of 15,000 units during August were as follows: The standard factory overhead rate is $7.50 per machine hour ($6.20 for variable factory overhead and $1.30 for fixed factory overhead)  based on 100% of normal capacity of 80,000 machine hours. The standard cost and the actual cost of factory overhead for the production of 15,000 units during August were as follows:   What is the amount of the fixed factory overhead volume variance? A)  $12,000 unfavorable B)  $12,000 favorable C)  $14,000 unfavorable D)  $26,000 unfavorable What is the amount of the fixed factory overhead volume variance?


A) $12,000 unfavorable
B) $12,000 favorable
C) $14,000 unfavorable
D) $26,000 unfavorable

E) A) and B)
F) C) and D)

Correct Answer

verifed

verified

Showing 61 - 80 of 166

Related Exams

Show Answer