Correct Answer
verified
Multiple Choice
A) $41.25
B) $45.84
C) $50.93
D) $56.59
E) $62.88
Correct Answer
verified
Multiple Choice
A) $134.79
B) $141.89
C) $149.36
D) $164.29
E) $205.36
Correct Answer
verified
Multiple Choice
A) 2.03 years
B) 2.25 years
C) 2.50 years
D) 2.75 years
E) 3.03 years
Correct Answer
verified
Multiple Choice
A) 1.91 years
B) 2.12 years
C) 2.36 years
D) 2.59 years
E) 2.85 years
Correct Answer
verified
Multiple Choice
A) Ignores cash flows beyond the payback period.
B) Does not directly account for the time value of money.
C) Does not provide any indication regarding a project's liquidity or risk.
D) Does not take account of differences in size among projects.
E) Lacks an objective, market-determined benchmark for making decisions.
Correct Answer
verified
Multiple Choice
A) $188.68
B) $198.61
C) $209.07
D) $219.52
E) $230.49
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) 9.43%
B) 9.91%
C) 10.40%
D) 10.92%
E) 11.47%
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) 14.05%
B) 15.61%
C) 17.34%
D) 19.27%
E) 21.20%
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) 1.61 years
B) 1.79 years
C) 1.99 years
D) 2.22 years
E) 2.44 years
Correct Answer
verified
Multiple Choice
A) $250.15
B) $277.94
C) $305.73
D) $336.31
E) $369.94
Correct Answer
verified
Multiple Choice
A) $92.37
B) $96.99
C) $101.84
D) $106.93
E) $112.28
Correct Answer
verified
Multiple Choice
A) You should delay a decision until you have more information on the projects, even if this means that a competitor might come in and capture this market.
B) You should recommend Project R, because at the new WACC it will have the higher NPV.
C) You should recommend Project K, because at the new WACC it will have the higher NPV.
D) You should recommend Project K because it has the higher IRR and will continue to have the higher IRR even at the new WACC.
E) You should reject both projects because they will both have negative NPVs under the new conditions.
Correct Answer
verified
Multiple Choice
A) Project L.
B) Both projects are equally sensitive to changes in the WACC since their NPVs are equal at all costs of capital.
C) Neither project is sensitive to changes in the discount rate, since both have NPV profiles that are horizontal.
D) The solution cannot be determined because the problem gives us no information that can be used to determine the projects' relative IRRs.
E) Project S.
Correct Answer
verified
Multiple Choice
A) A project's MIRR is always less than its regular IRR.
B) If a project's IRR is greater than its WACC, then the MIRR will be less than the IRR.
C) If a project's IRR is greater than its WACC, then the MIRR will be greater than the IRR.
D) To find a project's MIRR, we compound cash inflows at the IRR and then discount the terminal value back to t = 0 at the WACC.
E) A project's MIRR is always greater than its regular IRR.
Correct Answer
verified
Multiple Choice
A) The NPV method assumes that cash flows will be reinvested at the risk-free rate, while the IRR method assumes reinvestment at the IRR.
B) The NPV method assumes that cash flows will be reinvested at the WACC, while the IRR method assumes reinvestment at the risk-free rate.
C) The NPV method does not consider all relevant cash flows, particularly cash flows beyond the payback period.
D) The IRR method does not consider all relevant cash flows, particularly cash flows beyond the payback period.
E) The NPV method assumes that cash flows will be reinvested at the WACC, while the IRR method assumes reinvestment at the IRR.
Correct Answer
verified
Multiple Choice
A) $32.12
B) $35.33
C) $38.87
D) $40.15
E) $42.16
Correct Answer
verified
Showing 1 - 20 of 108
Related Exams