Correct Answer
verified
Multiple Choice
A) $5.47
B) $6.02
C) $6.62
D) $7.29
E) $7.82
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) the discounted payback method eliminates all of the problems associated with the payback method.
B) when evaluating independent projects, the npv and irr methods often yield conflicting results regarding a project's acceptability.
C) to find the mirr, we discount the tv at the irr.
D) a project's npv profile must intersect the x-axis at the project's cost of capital.
E) the irr method appeals to some managers because it gives an estimate of the rate of return on projects rather than a dollar amount, which the npv method provides.
Correct Answer
verified
Multiple Choice
A) if project a's irr exceeds project b's, then a must have the higher npv.
B) a project's mirr can never exceed its irr.
C) if a project with normal cash flows has an irr less than the cost of capital, the project must have a positive npv.
D) if the npv is negative, the irr must also be negative.
E) if a project with normal cash flows has an irr greater than the cost of capital, the project must also have a positive npv.
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) 12.55%
B) 13.21%
C) 13.87%
D) 14.56%
E) 15.29%
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) the irr method can never be subject to the multiple irr problem, while the mirr method can be.
B) one reason some people prefer the mirr to the regular irr is that the mirr is based on a generally more reasonable reinvestment rate assumption.
C) the higher the cost of capital, the shorter the discounted payback period.
D) the mirr method assumes that cash flows are reinvested at the crossover rate.
E) the mirr and npv decision criteria can never conflict.
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) 14.08%
B) 15.65%
C) 17.21%
D) 18.94%
E) 20.83%
Correct Answer
verified
Multiple Choice
A) project l.
B) both projects are equally sensitive to changes in the cost of capital since their npvs are equal at all costs of capital.
C) neither project is sensitive to changes in the discount rate, since both have npv profiles that are horizontal.
D) the solution cannot be determined because the problem gives us no information that can be used to determine the projects' relative irrs.
E) project s.
Correct Answer
verified
True/False
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) a project's regular irr is found by compounding the cash inflows at the cost of capital to find the present value (pv) , then discounting the tv to find the irr.
B) if a project's irr is smaller than the cost of capital, then its npv will be positive.
C) a project's irr is the discount rate that causes the pv of the inflows to equal the project's cost.
D) if a project's irr is positive, then its npv must also be positive.
E) a project's regular irr is found by compounding the initial cost at the cost of capital to find the terminal value (tv) , then discounting the tv at the cost of capital.
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) it will accept too many long-term projects and reject too many short-term projects (as judged by the npv) .
B) the firm will accept too many projects in all economic states because a 4-year payback is too low.
C) the firm will accept too few projects in all economic states because a 4-year payback is too high.
D) if the 4-year payback results in accepting just the right set of projects under average economic conditions, then this payback will result in too few long-term projects when the economy is weak.
E) it will accept too many short-term projects and reject too many long-term projects (as judged by the npv) .
Correct Answer
verified
Multiple Choice
A) you should delay a decision until you have more information on the projects, even if this means that a competitor might come in and capture this market.
B) you should recommend project r, because at the new cost of capital it will have the higher npv.
C) you should recommend project k, because at the new cost of capital it will have the higher npv.
D) you should recommend project r because it will have both a higher irr and a higher npv under the new conditions.
E) you should reject both projects because they will both have negative npvs under the new conditions.
Correct Answer
verified
Multiple Choice
A) one drawback of the regular payback for evaluating projects is that this method does not properly account for the time value of money.
B) if a project's payback is positive, then the project should be rejected because it must have a negative npv.
C) the regular payback ignores cash flows beyond the payback period, but the discounted payback method overcomes this problem.
D) if a company uses the same payback requirement to evaluate all projects, say it requires a payback of 4 years or less, then the company will tend to reject projects with relatively short lives and accept long-lived projects, and this will cause its risk to increase over time.
E) the longer a project's payback period, the more desirable the project is normally considered to be by this criterion.
Correct Answer
verified
Multiple Choice
A) you should delay a decision until you have more information on the projects, even if this means that a competitor might come in and capture this market.
B) you should recommend project r, because at the new cost of capital it will have the higher npv.
C) you should recommend project k, because at the new cost of capital it will have the higher npv.
D) you should recommend project k because it has the higher irr and will continue to have the higher irr even at the new cost of capital.
E) you should reject both projects because they will both have negative npvs under the new conditions.
Correct Answer
verified
Showing 61 - 80 of 108
Related Exams