A) $10,521
B) $11,075
C) $11,658
D) $12,271
E) $12,885
Correct Answer
verified
Multiple Choice
A) $15,925
B) $16,764
C) $17,646
D) $18,528
E) $19,455
Correct Answer
verified
Multiple Choice
A) $55.08
B) $57.98
C) $61.03
D) $64.08
E) $67.29
Correct Answer
verified
Multiple Choice
A) project b, which has below-average risk and an irr = 8.5%.
B) project c, which has above-average risk and an irr = 11%.
C) without information about the projects' npvs we cannot determine which project(s) should be accepted.
D) all of these projects should be accepted.
E) project a, which has average risk and an irr = 9%.
Correct Answer
verified
True/False
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) in a capital budgeting analysis where part of the funds used to finance the project would be raised as debt, failure to include interest expense as a cost when determining the project's cash flows will lead to a downward bias in the npv.
B) the existence of any type of "externality" will reduce the calculated npv versus the npv that would exist without the externality.
C) if one of the assets to be used by a potential project is already owned by the firm, and if that asset could be sold or leased to another firm if the new project were not undertaken, then the net after-tax proceeds that could be obtained should be charged as a cost to the project under consideration.
D) if one of the assets to be used by a potential project is already owned by the firm but is not being used, then any costs associated with that asset is a sunk cost and should be ignored.
E) in a capital budgeting analysis where part of the funds used to finance the project would be raised as debt, failure to include interest expense as a cost when determining the project's cash flows will lead to an upward bias in the npv.
Correct Answer
verified
Multiple Choice
A) $13,286
B) $13,985
C) $14,721
D) $15,457
E) $16,230
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) $23,852
B) $25,045
C) $26,297
D) $27,612
E) $28,993
Correct Answer
verified
Multiple Choice
A) $15,740
B) $16,569
C) $17,441
D) $18,359
E) $19,325
Correct Answer
verified
Multiple Choice
A) 1.20
B) 1.26
C) 1.32
D) 1.39
E) 1.46
Correct Answer
verified
Multiple Choice
A) the proposed new project would increase the firm's corporate risk.
B) the proposed new project would increase the firm's market risk.
C) the proposed new project would not affect the firm's risk at all.
D) the proposed new project would have less stand-alone risk than the firm's typical project.
E) the proposed new project would have more stand-alone risk than the firm's typical project.
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) since depreciation is a non-cash expense, the firm does not need to deal with depreciation when calculating the operating cash flows.
B) when estimating the project's operating cash flows, it is important to include both opportunity costs and sunk costs, but the firm should ignore the cash flow effects of externalities since they are accounted for in the discounting process.
C) capital budgeting decisions should be based on before-tax cash flows.
D) the cost of capital used to discount cash flows in a capital budgeting analysis should be calculated on a before-tax basis.
E) in calculating the project's operating cash flows, the firm should not deduct financing costs such as interest expense, because financing costs are accounted for by discounting at the cost of capital. if interest were deducted when estimating cash flows, this would, in effect, "double count" it.
Correct Answer
verified
Multiple Choice
A) $8,878
B) $9,345
C) $9,837
D) $10,355
E) $10,900
Correct Answer
verified
Multiple Choice
A) $8,903
B) $9,179
C) $9,463
D) $9,746
E) $10,039
Correct Answer
verified
Multiple Choice
A) $11,904
B) $12,531
C) $13,190
D) $13,850
E) $14,542
Correct Answer
verified
Multiple Choice
A) $28,115
B) $28,836
C) $29,575
D) $30,333
E) $31,092
Correct Answer
verified
True/False
Correct Answer
verified
Showing 1 - 20 of 78
Related Exams