A) To find the MIRR, we first compound cash flows at the regular IRR to find the TV, and then we discount the TV at the cost of capital to find the PV.
B) The NPV and IRR methods both assume that cash flows can be reinvested at the cost of capital. However, the MIRR method assumes reinvestment at the MIRR itself.
C) If two projects have the same cost, and if their NPV profiles cross in the upper right quadrant, then the project with the higher IRR probably has more of its cash flows coming in the later years.
D) If two projects have the same cost, and if their NPV profiles cross in the upper right quadrant, then the project with the lower IRR probably has more of its cash flows coming in the later years.
E) For a project with normal cash flows, any change in the cost of capital will change both the NPV and the IRR.
Correct Answer
verified
Multiple Choice
A) The discounted payback method recognizes all cash flows over a project's life, and it also adjusts these cash flows to account for the time value of money.
B) The regular payback method was, years ago, widely used, but virtually no companies even calculate the payback today.
C) The regular payback is useful as an indicator of a project's liquidity because it gives managers an idea of how long it will take to recover the funds invested in a project.
D) The regular payback does not consider cash flows beyond the payback year, but the discounted payback overcomes this defect.
E) The regular payback method recognizes all cash flows over a project's life.
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) $11.45
B) $12.72
C) $14.63
D) $16.82
E) $19.35
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) $41.25
B) $45.84
C) $50.93
D) $56.59
E) $62.88
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) −$59.03
B) −$56.08
C) −$53.27
D) −$50.61
E) −$48.08
Correct Answer
verified
Multiple Choice
A) 13.13%
B) 14.44%
C) 15.89%
D) 17.48%
E) 19.22%
Correct Answer
verified
Multiple Choice
A) 2.08%
B) 2.31%
C) 2.57%
D) 2.82%
E) 3.10%
Correct Answer
verified
Multiple Choice
A) 1.91 years
B) 2.12 years
C) 2.36 years
D) 2.59 years
E) 2.85 years
Correct Answer
verified
Multiple Choice
A) $138.10
B) $149.21
C) $160.31
D) $171.42
E) $182.52
Correct Answer
verified
Multiple Choice
A) A project's NPV increases as the cost of capital declines.
B) A project's MIRR is unaffected by changes in the cost of capital.
C) A project's regular payback increases as the cost of capital declines.
D) A project's discounted payback increases as the cost of capital declines.
E) A project's IRR increases as the cost of capital declines.
Correct Answer
verified
Multiple Choice
A) 1.88 years
B) 2.09 years
C) 2.29 years
D) 2.52 years
E) 2.78 years
Correct Answer
verified
Multiple Choice
A) You should delay a decision until you have more information on the projects, even if this means that a competitor might come in and capture this market.
B) You should recommend Project R, because at the new cost of capital it will have the higher NPV.
C) You should recommend Project K, because at the new cost of capital it will have the higher NPV.
D) You should recommend Project K because it has the higher IRR and will continue to have the higher IRR even at the new cost of capital.
E) You should reject both projects because they will both have negative NPVs under the new conditions.
Correct Answer
verified
Multiple Choice
A) 14.08%
B) 15.65%
C) 17.21%
D) 18.94%
E) 20.83%
Correct Answer
verified
Multiple Choice
A) If the cost of capital is 6%, Project S will have the higher NPV.
B) If the cost of capital is 13%, Project S will have the lower NPV.
C) If the cost of capital is 10%, both projects will have a negative NPV.
D) Project S's NPV is more sensitive to changes in cost of capital than Project L's.
E) If the cost of capital is 10%, both projects will have positive NPVs.
Correct Answer
verified
Multiple Choice
A) The lower the cost of capital used to calculate a project's NPV, the lower the calculated NPV will be.
B) If a project's NPV is less than zero, then its IRR must be less than the cost of capital.
C) If a project's NPV is greater than zero, then its IRR must be less than zero.
D) The NPV of a relatively low-risk project should be found using a relatively high cost of capital.
E) A project's NPV is found by compounding the cash inflows at the IRR to find the terminal value (TV) , then discounting the TV at the cost of capital.
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) $105.89
B) $111.47
C) $117.33
D) $123.51
E) $130.01
Correct Answer
verified
Showing 21 - 40 of 108
Related Exams