A) 13.42%
B) 14.91%
C) 16.56%
D) 18.22%
E) 20.04%
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) Project L.
B) Both projects are equally sensitive to changes in the cost of capital since their NPVs are equal at all costs of capital.
C) Neither project is sensitive to changes in the discount rate, since both have NPV profiles that are horizontal.
D) The solution cannot be determined because the problem gives us no information that can be used to determine the projects' relative IRRs.
E) Project S.
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) One defect of the IRR method is that it does not take account of the time value of money.
B) One defect of the IRR method is that it does not take account of the cost of capital.
C) One defect of the IRR method is that it values a dollar received today the same as a dollar that will not be received until sometime in the future.
D) One defect of the IRR method is that it assumes that the cash flows to be received from a project can be reinvested at the IRR itself, and that assumption is often not valid.
E) One defect of the IRR method is that it does not take account of cash flows over a project's full life.
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) A project's MIRR is always less than its regular IRR.
B) If a project's IRR is greater than its cost of capital, then the MIRR will be less than the IRR.
C) If a project's IRR is greater than its cost of capital, then the MIRR will be greater than the IRR.
D) To find a project's MIRR, we compound cash inflows at the IRR and then discount the terminal value back to t = 0 at the cost of capital.
E) A project's MIRR is always greater than its regular IRR.
Correct Answer
verified
Multiple Choice
A) Since the projects are mutually exclusive, the firm should always select Project B.
B) If the crossover rate is 8%, Project B will have the higher NPV.
C) Only one project has a positive NPV.
D) If the crossover rate is 8%, Project A will have the higher NPV.
E) Each project must have a negative NPV.
Correct Answer
verified
Showing 101 - 108 of 108
Related Exams