Filters
Question type

Study Flashcards

The standard costs and actual costs for direct materials for the manufacture of 2,500 actual units of product are as follows: The standard costs and actual costs for direct materials for the manufacture of 2,500 actual units of product are as follows:   The amount of the direct materials quantity variance is: A)  $875 favorable B)  $800 unfavorable C)  $800 favorable D)  $875 unfavorable The amount of the direct materials quantity variance is:


A) $875 favorable
B) $800 unfavorable
C) $800 favorable
D) $875 unfavorable

E) None of the above
F) A) and D)

Correct Answer

verifed

verified

The standard costs and actual costs for direct materials, direct labor, and factory overhead for the manufacture of 2,500 units of product are as follows: The standard costs and actual costs for direct materials, direct labor, and factory overhead for the manufacture of 2,500 units of product are as follows:   The amount of the direct labor time variance is: A)  $1,180 favorable B)  $1,140 unfavorable C)  $1,180 unfavorable D)  $1,140 favorable The amount of the direct labor time variance is:


A) $1,180 favorable
B) $1,140 unfavorable
C) $1,180 unfavorable
D) $1,140 favorable

E) A) and B)
F) None of the above

Correct Answer

verifed

verified

The standard price and quantity of direct materials are separated because:


A) GAAP reporting requires this separation
B) direct materials prices are controlled by the purchasing department, and quantity used is controlled by the production department
C) standard quantities are more difficult to estimate than standard prices
D) standard prices change more frequently than standard quantities

E) A) and B)
F) B) and C)

Correct Answer

verifed

verified

The standard costs and actual costs for factory overhead for the manufacture of 2,500 units of actual production are as follows: The standard costs and actual costs for factory overhead for the manufacture of 2,500 units of actual production are as follows:   The amount of the total factory overhead cost variance is: A)  $2,000 favorable B)  $5,000 unfavorable C)  $2,500 unfavorable D)  $0 The amount of the total factory overhead cost variance is:


A) $2,000 favorable
B) $5,000 unfavorable
C) $2,500 unfavorable
D) $0

E) A) and B)
F) None of the above

Correct Answer

verifed

verified

The variance from standard for factory overhead resulting from incurring a total amount of factory overhead cost that is greater or less than the amount budgeted for the level of operations achieved is termed controllable variance.

A) True
B) False

Correct Answer

verifed

verified

Standard and actual costs for direct labor for the manufacture of 1,000 units of product were as follows: Standard and actual costs for direct labor for the manufacture of 1,000 units of product were as follows:

Correct Answer

verifed

verified

Determine the (a) time varianc...

View Answer

If the standard to produce a given amount of product is 1,000 units of direct materials at $11 and the actual was 800 units at $12, the direct materials price variance was $800 unfavorable.

A) True
B) False

Correct Answer

verifed

verified

The following data relate to direct labor costs for the current period: The following data relate to direct labor costs for the current period:   What is the direct labor rate variance? A)  $2,250.00 unfavorable B)  $2,125.00 unfavorable C)  $2,250.00 favorable D)  $2,125.00 favorable What is the direct labor rate variance?


A) $2,250.00 unfavorable
B) $2,125.00 unfavorable
C) $2,250.00 favorable
D) $2,125.00 favorable

E) A) and B)
F) A) and C)

Correct Answer

verifed

verified

An example of a nonfinancial measure is the number of customer complaints.

A) True
B) False

Correct Answer

verifed

verified

A company must choice either a standard system or nonfinancial performance measures to evaluate the performance of a company.

A) True
B) False

Correct Answer

verifed

verified

Cost systems using detailed estimates of each element of manufacturing cost entering into the finished product are called standard cost systems.

A) True
B) False

Correct Answer

verifed

verified

If the standard to produce a given amount of product is 1,000 units of direct materials at $11 and the actual was 800 units at $12, the direct materials price variance was $800 favorable.

A) True
B) False

Correct Answer

verifed

verified

Japan Company produces lamps that require 2.25 standard hours per unit at an hourly rate of $15.00 per hour. If 7,700 units required 19,250 hours at an hourly rate of $14.90 per hour, what is the direct labor (a) rate variance, (b) time variance, and (c) cost variance?

Correct Answer

verifed

verified

(a) Rate variance = ($15.00 - $14.90) x ...

View Answer

Standards are designed to evaluate price and quantity variances separately.

A) True
B) False

Correct Answer

verifed

verified

Which of the following is not a reason for a direct materials quantity variance?


A) Malfunctioning equipment
B) Purchasing of inferior raw materials
C) Increased material cost per unit
D) Spoilage of materials

E) B) and D)
F) All of the above

Correct Answer

verifed

verified

The principle of exceptions allows managers to


A) focus on correcting variances between standard costs and actual costs.
B) focus on correcting variances between variable costs and actual costs.
C) focus on correcting variances between competitor's costs and actual costs.
D) focus on correcting variances between competitor's costs and standard costs.

E) None of the above
F) A) and C)

Correct Answer

verifed

verified

The St. Augustine Corporation originally budgeted for $360,000 of fixed overhead at 100% production capacity. Production was budgeted to be 12,000 units. The standard hours for production were 5 hours per unit. The variable overhead rate was $3 per hour. Actual fixed overhead was $360,000 and actual variable overhead was $170,000. Actual production was 11,700 units. Compute the factory overhead volume variance.


A) $9,000F
B) $9,000U
C) $5,500F
D) $5,500U

E) All of the above
F) A) and C)

Correct Answer

verifed

verified

  Calculate the Total Direct Materials cost variance using the above information: A)  $9,262.50 Unfavorable B)  $9,262.50 Favorable C)  $3,780.00 Unfavorable D)  $3,562.50 Favorable Calculate the Total Direct Materials cost variance using the above information:


A) $9,262.50 Unfavorable
B) $9,262.50 Favorable
C) $3,780.00 Unfavorable
D) $3,562.50 Favorable

E) A) and B)
F) A) and C)

Correct Answer

verifed

verified

The total manufacturing cost variance consists of:


A) Direct materials price variance, direct labor cost variance, and fixed factory overhead volume variance
B) Direct materials cost variance, direct labor rate variance, and factory overhead cost variance
C) Direct materials cost variance, direct labor cost variance, variable factory overhead controllable variance
D) Direct materials cost variance, direct labor cost variance, factory overhead cost variance

E) A) and B)
F) A) and C)

Correct Answer

verifed

verified

Trumpet Company produced 8,700 units of product that required 3.25 standard hours per unit. The standard variable overhead cost per unit is $4.00 per hour. The actual variance factory overhead was $111,000. Determine the variable factory overhead controllable variance.

Correct Answer

verifed

verified

(8,700 x 3.25 x $4.0...

View Answer

Showing 61 - 80 of 160

Related Exams

Show Answer